Screeding Quiz

Description

Quiz on Screeding Quiz, created by Steve Lockwood on 05/11/2014.
Steve Lockwood
Quiz by Steve Lockwood, updated more than 1 year ago
Steve Lockwood
Created by Steve Lockwood over 9 years ago
428
0

Resource summary

Question 1

Question
1. How much mixed material is needed to complete a floor screed 5.000 m long by 4.000 m wide and 0.050 m thick?
Answer
  • 0.25 m3
  • 0.5 m3
  • 1 m3
  • 1.5 m3

Question 2

Question
2. Tools and equipment for floor screeding will generally include:
Answer
  • sweeping brush, trowel, float, mixer, shovel
  • splash brush, small tool, gauger, trowel, float
  • spirit level, trowel, buckets, mixer, float
  • levelling equipment, trowel, float, shovel buckets, mixer

Question 3

Question
Plastic sheeting below the structural floor is the:
Answer
  • damp proof membrane
  • vapour barrier
  • moisture trap
  • aid to curing the floor

Question 4

Question
The type of cement used in floor screeds is:
Answer
  • Masonry Portland
  • Extra Portland
  • Rapid Portland
  • Ordinary Portland

Question 5

Question
Sands used for floor screeding:
Answer
  • should contain a high proportion of fine grains
  • should contain a high proportion of large grains
  • can be any type
  • should be sharp and well graded

Question 6

Question
Ready-mixed screeds are:
Answer
  • prepared off site and delivered as required
  • prepared after work for the following day
  • prepared in the morning for use during the day
  • used only for self-levelling floors

Question 7

Question
Screed rails or battens are used to:
Answer
  • help delivery of screed material to the workstation
  • assist in forming the main area of floor
  • tamp down the surface of the screed
  • form channels for drainage

Question 8

Question
The purpose of a damp proof membrane is to:
Answer
  • assist the passage of moisture
  • assist in the curing process
  • allow the screed to dry out quickly
  • prevent the passage of moisture

Question 9

Question
Cracking of large area floors may be reduced by:
Answer
  • use of more cement
  • use of expansion strips
  • adding more sand
  • a self-levelling compound

Question 10

Question
Battens used as a guide for screeds may be:
Answer
  • set out from datum lines
  • laid at 50 mm depth
  • set out from base floor
  • laid to form 75 mm depth

Question 11

Question
The most accurate proportioning of floor screeding materials:
Answer
  • is by weight
  • is important near heavily trafficked areas
  • can be carried out using shovels
  • can be carried out using buckets

Question 12

Question
The correct consistency for floor screeding materials is:
Answer
  • as dry as possible
  • slurry like
  • semi wet
  • semi dry

Question 13

Question
Mixing of screed material:
Answer
  • does not have to be thorough as it will be spread by shovel
  • needs to be consistent or wear will take place
  • should be carried out as slowly as possible
  • can take place after water has been added

Question 14

Question
Compacting screeds results in a:
Answer
  • lightweight screed
  • quicker set screed
  • more dense screed
  • slower set screed

Question 15

Question
Compacting can be carried out with a:
Answer
  • screed rail
  • datum
  • rule or float
  • level

Question 16

Question
High volumes of ventilation:
Answer
  • will aid the setting process
  • will not affect the screeds after laying
  • will allow the cement to harden quickly
  • may make the surface of the screed dusty

Question 17

Question
The finish on a floor screed:
Answer
  • is not important as it will all be covered up
  • is important as it may show through the final covering
  • can be completed the next day
  • can be completed by the floor layer with the finish

Question 18

Question
Laying polythene sheet on the floor screed after laying will:
Answer
  • act as an accelerator to the set
  • produce an even surface
  • allow the cement to set naturally
  • keep the floor soft for the next process

Question 19

Question
The purpose of curing is to:
Answer
  • allow the cement to set and harden over a long period
  • produce an even surface
  • produce a lightweight screed
  • aid compaction to take place

Question 20

Question
Where drainage outlets are fitted:
Answer
  • the floor must be laid from this point
  • they can be repositioned later
  • the floor can be altered to fit when finish is applied
  • the drainage contractor will alter them to suit
Show full summary Hide full summary

Similar

Area, Volume & Perimeter Mind Map
rory.examtime
Chemical Symbols
Keera
Physics
Holly Bamford
OCR Physics P4 Revision
Dan Allibone
English Basic Grammar
tvazacconcia
Language Techniques
Anna Wolski
Factores Humanos en la Aviación
Adriana Forero
Frankenstein - Mary Shelley
Johnny Hammer
DEV I Part I
d owen
MAPA MENTAL DISEÑO GRAFICO
puntoideascali
Účto Fífa 2/6
Bára Drahošová