canaldevbr com
Quiz by , created more than 1 year ago

Quiz on Scrum Master - Simulado 3 - Inglês, created by canaldevbr com on 08/05/2018.

121
0
0
canaldevbr com
Created by canaldevbr com over 6 years ago
Close

Scrum Master - Simulado 3 - Inglês

Question 1 of 20

1

John is the Product Owner, during the Daily he realized that the work is delayed. What should he do?

Select one of the following:

  • Nothing

  • Notify the CEO

  • Negotiate a reduction of the scope, guiding the team to focus on the goal

  • Cancel the sprint and change the team of developers

Explanation

Question 2 of 20

1

Frank is the Scrum Master and decided to cancel the Sprint. What should be the PO response?

Select one of the following:

  • Nothing

  • Do not accept cancellation as this is your prerogative

  • Agree with Scrum Master

Explanation

Question 3 of 20

1

Peter is a developer, tested in the user story and noticed a problem. Which action should Peter

Select one of the following:

  • Cancel user history

  • Notify the development team and fix the problem

  • Notify the test team

Explanation

Question 4 of 20

1

Is Product owner and Scrum master possible in the same person for the same project?

Select one of the following:

  • True
  • False

Explanation

Question 5 of 20

1

According to the Scrum guide, can we use parts of Scrum?

Select one of the following:

  • True
  • False

Explanation

Question 6 of 20

1

Can we change the size of the sprint during its execution?

Select one of the following:

  • True
  • False

Explanation

Question 7 of 20

1

The best scenario for using Scrum is?

Select one of the following:

  • Predictive

  • Complex and adaptative

  • Complex and predictive

  • All of these answers are correct

Explanation

Question 8 of 20

1

The maximum length of the Sprint Retrospective(its time box) is:

Select one of the following:

  • 3 hours for a monthly Sprint, proportionally less for shorter Sprints

  • 4 hours for a monthly Sprint, proportionally less for shorter Sprints

  • As long as needed

  • 1 day

Explanation

Question 9 of 20

1

How many meetings are defined in Scrum?

Select one of the following:

  • 1

  • 2

  • 3

  • 4

Explanation

Question 10 of 20

1

What is the purpose of the daily meeting?

Select one of the following:

  • Team meeting for inspection and adaptation

  • A formality of Scrum

  • To inform the Product Owner

  • None of the given answers

Explanation

Question 11 of 20

1

When does the development team create the sprint backlog?

Select one of the following:

  • daily

  • planning

  • review

  • retrospective

Explanation

Question 12 of 20

1

At the end of the sprint is a product increment that will go into production?

Select one of the following:

  • True
  • False

Explanation

Question 13 of 20

1

After the start of the sprint, what product owner will do?

Select one of the following:

  • Estimate the tasks

  • Support the team in the current sprint and detail the next sprint

  • Answer the three questions on the daily

Explanation

Question 14 of 20

1

Is it true that the Scrum Master is responsible for the ROI of the product?

Select one of the following:

  • True
  • False

Explanation

Question 15 of 20

1

What is the role of the project manager in the Scrum framework?

Select one of the following:

  • Control the timeline

  • Delegate tasks

  • There is no such role in the framework

Explanation

Question 16 of 20

1

When to cancel a sprint?

Select one of the following:

  • When dev team can not deliver

  • When sprint ends

  • When the goal does not make more sense

Explanation

Question 17 of 20

1

Scrum master ensures that Scrum is being applied correctly?

Select one of the following:

  • True
  • False

Explanation

Question 18 of 20

1

How does the product owner help the development team?

Select one of the following:

  • Detailed all product backlog

  • Clearing up doubts about backlog items

  • With the help of requirements analyst

  • He does not help the team.

Explanation

Question 19 of 20

1

When a backlog item was set to high priority, for what situation should it be considered?

Select one of the following:

  • Definition of done

  • Definition of Timebox

  • Definition of ready

  • None of the answers

Explanation

Question 20 of 20

1

Does the development team need to be multifunctional?

Select one of the following:

  • True
  • False

Explanation